Ongoing and Forthcoming Roadworks

This page is intended to summarise roadworks and traffic restrictions based on the information we receive from Via, Highways England and other organisations. Although we endeavour to ensure the information is accurate, we cannot be held responsible for any errors or omissions.

Roadworks and Traffic Restrictions

  • Bingham Market Place – Signing Works for Speed limit and One Way

    Bingham Town Council have been updated that the work in Bingham Market Place to add permanent signage for the one-way system and speed limit, are due to commence on Monday 25 April 2022.

    There may be some localised footway closures to enable the installation of the new signing and work will not take on Thursday due to the market. The laying of the new lines and buff coloured surfacing is expected to take place on Sunday morning to minimise disruption to local businesses.

     

  • Lane Closure on Chapel Lane (at Roundabout), 28 April

    There will be a lane closure on Chapel Lane at its junction with Margidunum roundabout on the 28th of April, 9:00am until 3:30pm. Please see the attached document for further information.

  • Lane Closure on Fosse Way, 25-26 April

    A lane will be closed on Fosse Way on the 25th and 26th of April, 9:00am through 3:30pm, for surveying work. Please see the attached document for further information.

  • Chapel Lane closed at level crossing, 9-19 May (UPDATED: Now ends 20 May)

    Chapel Lane (from the level crossing to the site of the new leisure centre) will be closed to traffic from Monday the 9th of May until Thursday the 20th of May. Please see the attached document for further information, including a map of the diversion route.

  • Update on essential maintenance works on the A52 (M1 junction 25 to A1 Barrowby)

    National highways:

    Further to previous works notifications, we write to advise you that the A52 between the M1 Junction 25 and the A1 at Barrowby scheme is now being re-scheduled.

    The scheme has been re-scheduled to avoid potential clashes with other road works along the A52 and due to lost time due to unforeseen weather conditions. This strategy minimises disruption and confusion wherever possible with regards to works traffic diversions.

    When will the work take place?

    We will work overnight between 8pm and 6am as per the locations and dates outlined below.

    • A52 Westbound Queens Drive Exit Slip – 14th – 15th March
    • A52 Eastbound Priory Roundabout to QMC – 15th – 16th March
    • A52 Eastbound & Westbound Bingham to Barrowby – 4th – 9th April

    Please see the attached document for further information.

  • Level crossing closed overnight 17-18 April, Kirk Hill/Chapel Lane

    Bingham level crossing will be closed at Kirk Hill/Chapel Lane from 10:30pm on Sunday the 17th of April until 5:00am on Monday the 18th of April. Please see the attached document for further information.

  • Market Street partial road closure and restrictions, overnight, 4-5 April

    Access to Market street will be restricted from 9:00pm, Monday the 4th of April until 6:00am, Tuesday the 5th of April:

    • Temporary prohibition of driving: between its junctions with Union Street and Long Acre
    • Temporary prohibition of waiting and suspension of one-way: between its junctions with Market Place and Union Street

    Please see the attached document for further information.

     

  • Swallow Drive Temporary Road Closure, 4th of April

    Swallow Drive (between its junctions with Kestrel Drive and Avocet Close) will be closed temporarily between 8:00am and 5:00pm on Monday the 4th of April to repair a manhole cover. Please see the attached document for further information.

  • Emergency Roadworks Bulletin: Temporary traffic signals on Nottingham Road

    Temporary traffic signals will be in place on Nottingham Road (at its junction with Brewsters Close) from today (4th February) until Tuesday the 8th of February to fix a burst water main. Please see the attached document for further information.

  • UPDATED: Temporary traffic signals on Chapel Lane, 19th of January to 11th of March (previously 3rd March)

    Temporary traffic signals will be in place on Chapel Lane (95 meters North of the turning for Dunsmore Avenue) from Wednesday the 19th of January until Friday the 11th of March, between 8:00am and 6:00pm. Please see the attached document for further information.

    Updated 1/3/2022: Works have been extended until the 11th of March.